It is informed to the Public that at presently no subsidy is available for Grid Connected Rooftop Solar Power Plants and the approval of the Cabinet to implement the new programme may please be read at http://pib.nic.in/PressReleaseIframePage.aspx?PRID=1565288. As and when MNRE,GOI will implement new programme then the same will be informed to the public    |    CHECKLIST OF DOCUMENT REQUIRED FOR RELEASE OF SUBSIDY FOR THE INSTALLATION OF SPV POWER PLANT.   (View / Download)
Beneficiaries /EPC companies are required to submit hard copies of all reports along with necessary certificates in PEDA Office in addition to online submission for release of subsidy otherwise no subsidy will be released



Approved L1 Rates for Subsidy

             Approved L1 rates for Grid connected  Rooftop Solar Power Plant (FY 2018-19)

Sr. No.

Category of Systems

Lowest offered price/ KW

Subsidy 30% as per L1 rates/  KW

1.

1 to 10 KWp

57751

17325

2.

>10 to 20 KWp

55000

16500

3.

>20 to 50 KWp

53351

16005

4.

>50 to 100 KWp

47983

14394

5.

>100 to 500 KWp

45991

13797

Note: The subsidy will be released @30% on L1 rates or actual expenditure incurred by the beneficiary whichever is lower. The release of subsidy would depend on availability of funds from MNRE, GOI and It is informed that at presently there is no subsidy/ Central Financial Assistance is available from MNRE, GOI. Before installation of the rooftop solar plant (Net Metering) it is suggested that you may please check from www.solarpunjab.com website regarding availability of subsidy/CFA.

;